Project News

Let's Get Rolling! - Work to Recommence on 'The Unknown Warrior'

From 1st July, the engineers at the West Shed will be restarting work on 5551 'The Unknown Warrior' after the enforced lockdown. We are appealing for your help in partnership with our friends at the Princess Royal Class Locomotive Trust.

With the PRCLT fleet including No. 6233 ‘Duchess of Sutherland’ not earning any hire fees for the foreseeable future, your kind generosity will not only see progress on ‘The Unknown Warrior’, it will crucially help to support the PRCLT in what continues to be difficult times for the preservation movement.

MONTHLY BULLETIN - May 2020

This Bulletin comes hard on the heels of the latest Warrior magazine, whose distribution has taken a little longer than usual because of the coronavirus emergency. (It was mailed to members on June 1st)

On the engineering front, the good news is that West Shed is still expected to re-open on the 1st July.  Our contract is now signed and plans are being made in conjunction with PRCLT to establish task priorities. Funding has been agreed for three months and will continued to be managed carefully on a rolling basis.

At HBSS, we have very recently paused the work for the time being for budget reasons, but good progress has been made on the cladding.

Join Now as a Member Using Our New Web Sign up Page

You can now easily join The LMS-Patriot Project as a Member using our new web sign up page on our website. Simply click here to join up, then choose your required Membership type, starting from £25 for single Membership, then fill in the form on the screen with all your details. Once completed you will be directed to our secure PayPal page where you can pay your Membership Fee with optional Donation to the Project.

Members receive our award winning quarterly magazine - The Warrior, Membership Card, Membership Certificate, and an invitation to Members' Day to view the latest progress with 5551 'The Unknown Warrior'.

MONTHLY BULLETIN - APRIL 2020

The Coronavirus pandemic continues to circumscribe our scope for making progress in most aspects of the Project’s activities, but I’m very pleased to be able to report that we are not yet, at least, at a complete standstill. 

Although all work at West Shed has ceased, HBSS continue, on a reduced work-basis, to work on the boiler cladding.  Further work has been approved, but will be on hold until HBSS can return to full-strength operations.  Whilst at Leaky Finders, work on the tender frames should be completed imminently.  A number of components - the dome and cover, heater-header and bracket, reverser assembly, among others, have been completed and are ready for delivery to West Shed from various contractors as soon as conditions allow. 

MONTHLY BULLETIN - MARCH 2020

This Bulletin is dominated by how the Coronavirus emergency is impacting on the project.

We are pleased to say that our partners at HBSS are at the time of writing continuing to work on the project, making steady progress with fitting the stays and working on the cladding assembly. Elsewhere, the dome and cover have passed their safety tests, but it is likely that the shut down will prevent transportation for machining and then return to HBSS. 

Pages

The LMS-Patriot Company Ltd. • Civic Centre, Riverside, Stafford, ST16 3AQ
Registered in England & Wales No. 6502248 • Registered Charity No. 1123521
Tel 01785 244156
All content copyright ©2024 The LMS-Patriot Company Ltd.
website by amber