MEMBERS' MONTHLY BULLETIN NOVEMBER 2022

The Warrior Magazine

We expect to despatch The Warrior Issue 55 to you on Monday 5th  December. The magazine contains a full account of the proceedings of our Annual General Meeting, which was held on 12th November at Kidderminster Railway Museum.

Engineering

I will not repeat here the general engineering progress reported in The Warrior. However, since the Warrior went to press the repair work on the outside cylinders has now been completed, and all quality documentation required has been supplied, by Cast Iron Welding Services.

Finance 

Members' Monthly Bulletin October 2022

Engineering

Following recent discussions with William Cook Cast Products, proof machining of the new wheels has required further engineering drawings: after some resource problems this has now been completed and we are in active contact with the supplier this week to progress completion.Salvage of the usable components from the original wheelsets (balance weights and crank pins) has now been completed at West Shed. The long-awaited replacement driving wheel axle has now been shipped from South Africa and is en route to the UK. 

Finance

Main Line Steam Builders Group holds Second Meeting

Six high-profile steam project groups with the common objective of delivering their respective locomotives fit for UK main line running have held a successful second meeting at CTL Seal Ltd in Sheffield.

All of the founder members attended :

Great Central Railway 'Last Hurrah' Loughborough Railway Station

The LMS Patriot New Build Project will have its sales stall open at Loughborough Railway Station throughout this event.

Good chance to buy those Christmas presents before our mobile stalls cease for the remainder of this year, apart from our presence at the Warley Model Railway Exhibition the following weekend.

Engineering Update - August 2022

ENGINEERING REPORT – August 2022

Members Monthly Bulletin September 2022

Engineering

Over recent weeks management work on the planning and arrangement of important next steps for the chassis reassembly at West Shed has been unavoidably restricted by staff availability and unscheduled operations for 6233. However a West Shed team meeting this week agreed a set of actions, including progressing detailed arrangements for component testing with Boro Foundry and for wheelset assembly at South Devon Railway Engineering.  Arrangements for dragbox and rear cylinder cover replacement were also approved. 

Gauge O Guildex 2022

The LMS Patriot Project will have its sales stall open on both days of this event.

It is being held at Bingley Hall, Stafford Showground, Weston Road, Stafford, ST18 0BD.

Entrance. Members £10.00 Public £15.00

Please note open to 17.00 on Saturday.

Barrow Hill 150 + 2 Open Weekend

The LMS Patriot Project will have its sales stall open throughout this event.

It is being held at Barrow Hill Roundhouse, Campbell Drive, Barrow Hill, Chesterfield, S43 2AR.

Adults £15, Children £8, Family £44 (2 adults 3 kids)

Members Monthly Bulletin - July 2022

Finance

At the first board meeting of the new financial year on 30 July a summary of our Quarter 1 results for 2022/2023 along with the accounts for 2021/22 was presented to the board for approval.

Prior to that, a meeting was held with our accountants at their offices in Stafford to receive their verdict:

‘The total income for the year showed a reduction from that in 2020/2021.  However, the charity has fared very well through the pandemic and is emerging in a healthy cash position. Now looking forward to external events coming back online and to utilising the cash reserves to progress work on the engine.’

Pages

Subscribe to The LMS-Patriot Project RSS
The LMS-Patriot Company Ltd. • Civic Centre, Riverside, Stafford, ST16 3AQ
Registered in England & Wales No. 6502248 • Registered Charity No. 1123521
Tel 01785 244156
All content copyright ©2026 The LMS-Patriot Company Ltd.
website by amber
Follow us Facebook link